Approximately 1,300 SF of renovated laboratory space, designed around physics and laser experiments. Work included demolition of existing finishes and MEP systems, and installation of new casework, fume hood, MEP systems, overhead unistrut equipment racks and architectural finishes.
The project was delivered under a lump sum design-build process, which was a new delivery model for UCSD. To satisfy the client’s needs, the project had an aggressive schedule with just over 90 days for the construction phase.
Please include your contact information and any related documents below to apply for the position below.