Lean construction techniques contributed to project efficiencies, including meeting TCO despite three-week permitting delay.

Tenant improvement expansion and existing clinic space remodel. Scope included 1) repurposing of 3,062 sq. ft. of space in Building 1, an existing PAMF clinic, for imaging modalities (one MRI, one CT scanner); and 2) improving 33,000 sq. ft. of leased shelled space in Building 2.

The project included relocating 12 specialties from Building 1 to Building 2; performing infrastructure upgrades to both buildings, and implementing an IT/telecom infrastructure.

Lean construction techniques included Last Planner scheduling and Percent Plan Complete.

Design-build MEP.

Related Services

Preconstruction

Lean Construction

Design-Build

Design Assist/Design-Build MEP+

EMAIL UPDATES

Signup with your email address below and we will keep you up to date on the latest Level 10 Construction news and project achievements (new , recently completed, awards and recognition)

Thank you for signing up

Project Executive

Kevin Englund

Partner/VP Operations